GRH were employed to carry out pipe alterations to two chillers at Nestle Gatwick.

 

nestleproj
 
GRH were employed to carryout the 200mm pipe alterations to the first of two chillers to be replaced at Nestle Gatwick. Pipe freezing of the 200mm chilled water services was carried out on the day of the chiller replacement to enable fabricated sections to be installed allowing temporary chiller connections.
 
90% of the welding was measured and fabricated off site to limit on site hot works and speed up installation time.
 
Existing power & BMS supplies were disconnected and re-connected as part of our works.


Main Contractor: LH Plc
GRH Solutions Limited Operatives: 8
GRH Solutions Limited Contract Value: £21,000.00

 

Key Points

  • Thermal pipe insulation & trace heating

  • Chilled water pipe work

  • Power Supplies

  • Controls

  • Pipe Freezing
  
All work was completed to schedule and an exceptional standard.