Wokingham Project

GRH were employed to carryout the installation of new 65mm cooling water services.

 

Wokingham
 

GRH were employed to carryout the installation of new 65mm cooling water services to new engine test cells
100% of the welding was measured and fabricated off site to remove any need for on site hot works and speed up installation time.


Main Contractor: Envirosound
GRH Solutions Limited Operatives: 5
GRH Solutions Limited Contract Value: £14,000.00

 

Key Points

  • Cooling water pipe work

  • Water flushing & treatment

  
All work was completed to schedule and an exceptional standard.