This project marked our largest valued project to date.

GRH were awarded the Denison Block refurbishment at Brompton army barracks that included the employment of an independent consultant to undertake a thermal model of the Denison block to ascertain thermal losses and design a new heating & ventilation system for the entire block that consisted of training rooms and cinema room.

A bespoke control system was designed & installed along with a heating system served from an adjoining block via a new plant room and Lossnay heat recovery ventilation system.

During the works we were also awarded modifications to multiple domestic services and cold water storage tank replacement.

All new services were fully flushed and disinfected on completion before a full balance of the new heating & ventilation systems.

As part of our works we also designed and supplied all the external building fabric louvers & panels for the build team to install.

GRH Completed all works on schedule and in budget.

Services Provided

  • LTHW.
  • MWS.
  • HWS.
  • Ventilation.
  • Controls.
  • Balancing.
  • Water treatment.
  • Thermal insulation.
  • Louvers.
  • Building fabric.

Project Details

  • Main Contractor: Walker Construction
  • GRH solutions Ltd Contact: Aircool.
  • GRH Solutions Ltd operatives: 18
  • GRH Solutions Ltd Contract Value: £1.25m