LH-Plc awarded GRH the chilled water modifications to 2No chiller replacements at Lewisham Police Station. This included local power & control wiring modifications to extend services to the new chiller control panel locations.

All new 200mm chiller connection spools were fabricated off-site to limit the on-site need for hot works, only 3No 200mm positional flanges required on-site welding.

On completion all new services were balanced and thermally insulated with valve jackets applied.

GRH Completed all works on schedule.

Services Provided

  • Chilled water.
  • Power & controls.
  • Welding & fabrication.
  • Thermal insulation.
  • Balancing.

Project Details

  • Main Contractor: LH-Plc
  • GRH solutions Ltd Contact: LH-Plc
  • GRH Solutions Ltd operatives: 8
  • GRH Solutions Ltd Contract Value: £27,000.00