LH-Plc employed GRH to carry out the replacement of 2No existing failed FCU’s with the increase of chilled water services to 50mm. as part of these works the existing chilled water branches were frozen to allow the leaking branch valves to be replaced.

On completion all new works were balanced and thermally insulated.

GRH Completed all works on schedule.

Services Provided

  • Chilled water.
  • Water balancing.
  • Pipe freezing.
  • Thermal insulation.

Project Details

  • Main Contractor: LH-Plc
  • GRH solutions Ltd Contact: LH-Plc
  • GRH Solutions Ltd operatives: 8
  • GRH Solutions Ltd Contract Value: £8,000.00